Project 04Timber and stone restoration47°37′59″N 012°58′59″E
Stillwater Chapel
- Client
- Parish of St. Leonhard
- Location
- Bavaria, Germany
- Year
- 2022
- Area
- 410 m²
- Duration
- 14 months
- Structural engineer
- Kessler Tragwerk, Munich
01 — The projectBavaria, Germany, 2022
Restoration is mostly listening. The chapel told us what it needed.
Stillwater Chapel has stood on the bank of the Ache since 1712. By 2019 the spire was leaning eleven centimetres to the east, and water ran through the nave walls every spring.
We lifted the spire on a temporary steel frame, replaced the rotten base plates with oak felled in the same valley, and repointed the rubble walls with a hot lime mortar matched to the original.
The timber boathouse beside the chapel was rebuilt board by board, every plank numbered, stored and re-laid. The parish rang the bell again at Easter 2022.
Site 47°37′59″N 012°58′59″E


02 — Materials and specifications06 items
- Structure
- Rubble stone walls, oak roof frame
- Spire
- Lifted, re-levelled, new oak base plates
- Mortar
- Hot-mixed lime, matched by analysis
- Roof
- Larch shingles, hand-split
- Timber
- Oak from the same valley, air-dried
- Consent
- Bavarian State Office for Monuments
Next project — 05Hospitality · Split, Croatia
North Pier Hotel